Survey in Transmission Lines


                                 Survey Work

Peg Marking

1. Reconnaissance Survey ( Walk over Survey) 

 

This is Essential to fix up angle towers position tentatively also it is important to collect the field data of the transmission lines.

Conditions to Be consider are:-

a. The Route shall be shortest with minimum distance.

b. It is better to lay the line along with the road so as to have good approach for each locations.

c.The number of angle towers should be minimum as possible.

d. Cost of securing and clearing ROW should be minimum.

e. Crossing Line Transmission lines , Road crossing and Railway line crossing should be minimum with preferably at right angle.

f. It is necessary to collect the detailed data in hilly terrains and ground profile.

 2. Alignment Survey ( Preliminary Survey)

 The main objective of the detailed survey is to prepare longitudinal and cross sectional profiles of the approved alignments and to prepare route plan showing detailed deviation angles, important objects coming in the Right of Way.

General Consideration 

Detailed survey is distinctly done in two stages

1. Actual field observations taking level reading and calculating distance, level differences, deviation of angles, offset distance etc.

2. Plotting of profiles on graphs.

This is to be done with the help of Total Stations 

 3. Detailed Survey

 The main objective of the check survey of final survey is to do tower spotting,  preparation of tower schedule

Tower Spotting is mainly divided in to five operations:

1. Sag Tension Calculation.

The Span length i..e distance between two adjacent tower location is fixed with optimum level by considering various factors like Line voltage, ground clearances, conductor used, topography of the area, wind zone and cost of line material and project cost.

2. Preparation of Sag Templates.

Sag Templates  consist of the 

Cold of Uplift Curve:- Showing sag of conductor at minimum temperature level.

Hot Or Maximum Sag Curve:- sag of conductor at maximum temperature level.

Ground Clearances curve:- Curve drawn parallel at distance equal to specified minimum ground clearance.

 

LU = Sq.Root of { Cube of {L1+L2+L3.....} / {L1+L2+L3....}}

 

whrere L1,L2,L3 ... are diffrent span in the session.

 3. Application of sag Templates to decide optimum tower position on Survey chart.

4. Preparation of Structure limitation charts.

5. Deciding Type of Tower and Preparing Tower Schedule.

While Preparation of the tower Schedule following points are required.

= Angle of line deviation of the Tower

= whether it is to be used section tower or dead end tower.

= Sum of adjacent Span

= Weight Span of the Towers.

 

4. Final Survey/ Check Survey 

 - It is carried out to reconfirm the work during carried out at the time of detailed survey.

- To locate and Peg marking of the tower locations

- To give direction pegs.

  It also covers the soil investigation of representative site along with the route of the line to establish the distribution of Foundation in diffrent zone.

Wind Zones

   Wind                           Basic Wind Speed

   Zone                              (Vb) m/sec

 

  1               33

  2               39

  3               44

  4               47

  5               50

  6               55

 

Pit Marking

Excavation Marking

Directional Pegs are essential to have correct alignment of longitude and transverse directions.

M=B

C= M + Pit size

A= C/2

E= A*1.414 + C

D= Pit Size * 1.414 + C

 

These parameters are taken from drawings and based on that pit marking is to be done.

Right of Way


Sr. No.                          Transmission Line        ROW Width

                                              Voltage                    in Meter

1.                                             66 KV            18            

2.                                            110 KV                       22

3.                                            132 KV                       27

4.                                            220 KV                       35

5.                                            400 KV                       52

6.                                            500 KV                       52 (HVDC)

7.                                            800 KV                       85 

Comments

Popular posts from this blog

Foundations In Transmission Lines